Project Feature: Rook 1 Camp Pilot Project

  • Client: NexGen Energy          

  • Indigenous Partner: Buffalo River Development Corporation

  • Project Completion: 2024

  • Solvest Role: Procurement, Construction

Solvest partnered with Buffalo River Professional Services, representing the Buffalo River Dene Nation, to supply a solar pilot project at NexGen’s Rook 1 camp. Situated in northwestern Saskatchewan with no grid connection, Rook 1 is anticipated to contribute 20% of the global uranium supply and is the first uranium project to receive provincial approval in over 20 years. The camp is currently trucking in diesel for its power supply.

  • Location: Rook 1 Mine Camp, Saskatchewan

  • System Size: 22 kW DC Solar + Battery