
Project Feature: STLLR Gold Project
In 2025 Solvest will construct a containerized 200 kWh energy storage unit including batteries, inverters, and controls in Whitehorse prior to transportation to site on the winter road in 2025 with solar construction and commissioning in the spring. The power system is expected to save 51,000 litres of diesel per year, equivalent to 138 tonnes of CO2 emissions, an approximately 86% reduction in diesel consumption for STLLR Gold's camp power. Tlicho Investment Corporation received grant funding to purchase the assets and will lease them to STLLR.
Location: NWT
System Size: 88kW